Flight check of the reconfigured Centre Runway at Hong Kong International Airport (HKIA) was successfully completed, marking a key milestone of readiness for the three-runway operation, according to the Airport Authority Hong Kong (AAHK).Following the commissioning of the North Runway in November 2022, the Centre Runway has been temporarily closed for reconfiguration as part of the Three-runway System (3RS) development. The reconfiguration works include relevelling of the runway pavement to tie in with connecting taxiways, constructing new runway entry and exit taxiways, building new wrap-around taxiways at both ends of the Centre Runway, and more. The AAHK continued to target the commencement of operation with all three runways at HKIA before the end of this year as scheduled.